Ribbon concrete foundation

Installing a strip concrete foundation should begin with filling trenches with compacted sand and gravel. All layers should be done twenty centimeters. Next, the installation can be continued in several ways. You can make it easier, or more reliable, it depends on the choice of a person.

When all layers of crushed stone are laid, you can start performing a bribe with a cement mortar, the layer of which should not exceed ten centimeters. The solution must dry and gain strength within a week. Next, the reinforcement should be laid. If there is a need, then before laying it, it is possible to waterproof using materials such as roofing material and other materials that have the property of waterproofing.

To lay the reinforcement, first you need to perform the longitudinal and transverse reinforcement of its rods, which you need to tie with a knitting wire. After that, you need to trace the reinforcement is covered with anti -corrosion compounds. There are times when you have to use a more complex way of reinforcement, in other words, make armakars. This is required in cases where the walls and floors have too much weight.